Supreme Court Restores Arbitral Award, Says Government Entities Can't Get Special Treatment Under Section 34

20 Nov 2026 · Legal News · By LawQuorum

The Supreme Court has restored an arbitral award, ruling that courts cannot interfere with the amount decided by an arbitrator merely because the party ordered to pay is a government body. The court said an award cannot be cut down simply because the sum appears excessive.

The bench of Justice J. B. Pardiwala and Justice K. Vinod Chandran was hearing appeals in a dispute between a contractor and the Port Trust of Calcutta over dredging work at Sagar Island. The contract involved dredging the riverbed and shores to create a channel and basin for a shore-based pilot station. The work was completed by April 17, 2001, when the Port Trust's Chairman inaugurated the pilot station using the dredged channel.

The contractor said additional work became necessary because of 100% siltation, which required repeated dredging. It blamed the Port Trust for not providing correct data on the soil and for failing to build protective walls. The Port Trust, meanwhile, wanted the entire arbitral award set aside, but argued in the alternative that if additional work was found to have been done, the lower court's decision to pay 50% of the amount with 6% interest should be upheld.

A single judge under Section 34 of the Arbitration and Conciliation Act had affirmed the award, noting that additional work was evident from a letter dated July 19, 2000, sent by the Port Trust to the contractor. But a division bench under Section 37 later modified the award, cutting the amount to 50% and reducing interest to 6%, saying it was shocked by the size of the claim for additional work, which exceeded 70% of the original contract.

The Supreme Court found this modification unsustainable. It said the arbitrator's award was based on valid material, including measurements and invoices, and could not be called perverse or patently illegal. The division bench, it noted, had not examined the measurements or invoices, which would have amounted to deciding the merits of the case—something the 1996 Act prohibits at that stage. The court also pointed out that parties to an arbitration must be treated equally, and government entities cannot receive special treatment, even when a stay of a money decree is sought under Section 34.

Setting aside the division bench's order, the Supreme Court allowed the contractor's appeal and restored the arbitral award. The case was titled M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata.